Many of our users ask for an example list of Categories to start their project with. Here is our recommendation below - it can be edited or added to, or discarded entirely, depending on the needs of your project.

Indented categories below indicate a sub-category, a level of categories nested under the one above.

Change Order
Clean up
Daily Log
    Aerial Photography
    Delay
        Materials Delayed
        Trade Delay
        Weather Delay
Delivery
Demo
Grading
Inspections
In Wall
Materials
    Shortage
    Extra Materials
Progress
SWPPP
Unforeseen condition
Meeting Minutes
Punch List
    Patch and Paint
    Pre-Punch
    Repair Access Door
    Repair Acoustical Panel
    Repair Blocking
    Repair Framing
    Repair Insulation
    Repair Wall
    Repair/Replace Site Paving
    Replace Ceiling Tile
    Replace Slab
QA/QC
    Damage
    Poor Workmanship
    Water Damage/Leak
    Work to complete
RFI
Safety
    Proactive
    Temp Protection
    Toolbox Talk
    Weekly Memo
    Violation
        Missing Hardhat
        Missing Safety Glasses
        No Harness
Submittal
Schedule Impact
Warranty Work